Key Notices that may be of importance to your project.




|
What's New....
- Maricopa County now requires dust permits for all projects
exceeding 1/10 of an acre. Although, even if the project
disturbs less than 1/10 of an acre the full dust permit application
and be submitted for an exemption. For further information
please contact our office.
Click here for contact information
|
Key Notices....
- An excellent service has just gotten better. Feel free to
browse the "NEW" web site for Priority Permits. The
address is www.epermits.net.
You'll find form downloads, general information in regards to FAQ
and a request form so you can now submit for your permit request
online.
- If You have a home that has gas lines or
power lines that are or will be in the way of placement of a new
home installation keep in mind that electric companies can take
sometimes 2 weeks + to remove overhead lines and/or disconnects at
J-Boxes. Whereas a gas company could take anywhere from 6-8
weeks for main line disconnects. This can and will place a
strain on your project if these disconnects are not done in advance
of new home delivery.
|
|